
A can do a work in 10 days and B can do the same work in 15 days. How long will they take to complete the work if both work together?
Options: A) 6 days
B) 5 days
C) 8 days
D) 12 days
Answer: A) 6 days
Together, they can complete (1/10 + 1/15) of the work per day.
LCM of 10 and 15 = 30, so:
Together, they complete (3 + 2) = 5/30 of the work per day. Thus, they will take 30/5 = 6 days to complete the work.
If 8 men can do a piece of work in 12 days, how long will it take for 6 men to do the same work?
Options: A) 14 days
B) 16 days
C) 18 days
D) 20 days
Answer: B) 16 days
Explanation: The work done is inversely proportional to the number of men. So, the relationship can be represented as:Men1×Days1=Men2×Days2
Substituting the given values:8×12=6×Days2 96=6×Days2 Days2=96/6=16 day
A alone can complete a piece of work in 12 days, and B alone can complete the same work in 18 days. If A and B work together, in how many days will they finish the work?
A) 6 days
B) 7.2 days
C) 8 days
D) 10 days
Answer: A) 6 days
If 8 men can complete a job in 20 days, how many men will be required to complete the same job in 10 days?
A) 12
B) 16
C) 20
D) 24
Answer: B) 16
A and B can complete a task in 10 days together. A alone can complete it in 15 days. How long will B take to finish the work alone?
A) 20 days
B) 25 days
C) 30 days
D) 35 days
Answer: C) 30 days
A contractor hires 10 workers to complete a work in 40 days. After 10 days, he hires 5 more workers. In how many more days will the work be completed?
A) 20 days
B) 22 days
C) 24 days
D) 25 days
Answer: C) 24 days
A, B, and C together can complete a work in 6 days. A alone can do it in 12 days, and B alone can do it in 18 days. How long will C alone take to complete the work?
A) 9 days
B) 24 days
C) 36 days
D) 48 days
Answer: C) 36 days
A can do a piece of work in 16 days, while B can do the same work in 24 days. They started working together, but A left after 4 days. In how many more days will B complete the remaining work?
A) 10 days
B) 12 days
C) 14 days
D) 16 days
Answer: B) 12 days
Two pipes can fill a tank in 10 hours and 15 hours, respectively. A third pipe can empty the tank in 30 hours. If all three pipes are opened together, how long will it take to fill the tank?
A) 6 hours
B) 8 hours
C) 10 hours
D) 12 hours
Answer: B) 8 hours
A work is to be completed in 24 days, and 30 men were employed for it. But after 6 days, 10 more men were added. In how many days will the work be completed?
A) 16 days
B) 18 days
C) 20 days
D) 22 days
Answer: A) 16 days
Sample Quantitative Aptitude Question
Conclusion
Time and Work problems are essential in quantitative aptitude, testing a candidate’s ability to handle efficiency-based calculations. Understanding concepts like individual and group work efficiency, LCM method, and inverse proportionality can significantly improve problem-solving speed. Practicing a variety of questions helps in mastering different scenarios, such as pipes and cisterns or workforce changes.