Time and Work – Quantitative Aptitude Question

Time and Work – Quantitative Aptitude Question

Time and Work – Quantitative Aptitude Question

Question 1:

A can do a work in 10 days and B can do the same work in 15 days. How long will they take to complete the work if both work together?

Options: A) 6 days
B) 5 days
C) 8 days
D) 12 days

Answer: A) 6 days

Explanation:

  • A’s work rate = 1/10 (work done per day)
  • B’s work rate = 1/15 (work done per day)

Together, they can complete (1/10 + 1/15) of the work per day.

LCM of 10 and 15 = 30, so:

  • A’s rate = 3/30
  • B’s rate = 2/30

Together, they complete (3 + 2) = 5/30 of the work per day. Thus, they will take 30/5 = 6 days to complete the work.


Question 2:

If 8 men can do a piece of work in 12 days, how long will it take for 6 men to do the same work?

Options: A) 14 days
B) 16 days
C) 18 days
D) 20 days

Answer: B) 16 days

Explanation: The work done is inversely proportional to the number of men. So, the relationship can be represented as:Men1×Days1=Men2×Days2

Substituting the given values:8×12=6×Days2 96=6×Days2​ Days2=96/6=16 day


Question 3:

A alone can complete a piece of work in 12 days, and B alone can complete the same work in 18 days. If A and B work together, in how many days will they finish the work?

A) 6 days

B) 7.2 days

C) 8 days

D) 10 days

Answer: A) 6 days

Solution:

  • Work done by A in 1 day = 1/12
  • Work done by B in 1 day = 1/18
  • Work done by A and B together in 1 day = (1/12) + (1/18) = (3 + 2) / 36 = 5/36
  • Total days to complete the work = 36/5 = 7.2 days

Question 4:

If 8 men can complete a job in 20 days, how many men will be required to complete the same job in 10 days?

A) 12

B) 16

C) 20

D) 24

Answer: B) 16

Solution:

  • Work = 8 men × 20 days = 160 man-days
  • Required number of men = 160 man-days / 10 days = 16 men

Question 5:

A and B can complete a task in 10 days together. A alone can complete it in 15 days. How long will B take to finish the work alone?

A) 20 days

B) 25 days

C) 30 days

D) 35 days

Answer: C) 30 days

Solution:

  • Work done by A and B together in 1 day = 1/10
  • Work done by A alone in 1 day = 1/15
  • Work done by B alone in 1 day = (1/10) – (1/15) = (3 – 2) / 30 = 1/30
  • So, B alone takes 30 days to complete the work.

Question 6:

A contractor hires 10 workers to complete a work in 40 days. After 10 days, he hires 5 more workers. In how many more days will the work be completed?

A) 20 days

B) 22 days

C) 24 days

D) 25 days

Answer: C) 24 days

Solution:

  • Total work = 10 workers × 40 days = 400 worker-days
  • Work done in 10 days = 10 × 10 = 100 worker-days
  • Work remaining = 400 – 100 = 300 worker-days
  • Now, 15 workers are working. Time required = 300/15 = 20 days
  • Total additional days = 20 days

Question 6:

A, B, and C together can complete a work in 6 days. A alone can do it in 12 days, and B alone can do it in 18 days. How long will C alone take to complete the work?

A) 9 days

B) 24 days

C) 36 days

D) 48 days

Answer: C) 36 days

Solution:

  • Work done by A, B, and C together in 1 day = 1/6
  • Work done by A alone in 1 day = 1/12
  • Work done by B alone in 1 day = 1/18
  • Work done by C alone in 1 day = (1/6) – (1/12) – (1/18)
    • LCM of 6, 12, and 18 = 36
    • (6 – 3 – 2) / 36 = 1/36
  • So, C alone will take 36 days.

A can do a piece of work in 16 days, while B can do the same work in 24 days. They started working together, but A left after 4 days. In how many more days will B complete the remaining work?

A) 10 days

B) 12 days

C) 14 days

D) 16 days

Answer: B) 12 days

Solution:

  • Work done by A in 1 day = 1/16
  • Work done by B in 1 day = 1/24
  • Work done by A and B together in 1 day = (1/16) + (1/24) = (3 + 2) / 48 = 5/48
  • Work done by A and B in 4 days = 4 × (5/48) = 20/48 = 5/12
  • Work remaining = 1 – 5/12 = 7/12
  • Time taken by B alone to finish 7/12 of the work = (7/12) ÷ (1/24) = (7/12) × 24 = 12 days

Question 7:

Two pipes can fill a tank in 10 hours and 15 hours, respectively. A third pipe can empty the tank in 30 hours. If all three pipes are opened together, how long will it take to fill the tank?

A) 6 hours

B) 8 hours

C) 10 hours

D) 12 hours

Answer: B) 8 hours

Solution:

  • Work done by first pipe in 1 hour = 1/10
  • Work done by second pipe in 1 hour = 1/15
  • Work done by third pipe in 1 hour (emptying) = -1/30
  • Net work done in 1 hour = (1/10) + (1/15) – (1/30)
    • LCM of 10, 15, and 30 = 30
    • (3 + 2 – 1) / 30 = 4/30 = 2/15
  • Time required to fill the tank = 15/2 = 7.5 hours

Question 8:

A work is to be completed in 24 days, and 30 men were employed for it. But after 6 days, 10 more men were added. In how many days will the work be completed?

A) 16 days

B) 18 days

C) 20 days

D) 22 days

Answer: A) 16 days

Solution:

  • Total work = 30 men × 24 days = 720 man-days
  • Work done in 6 days = 30 × 6 = 180 man-days
  • Work remaining = 720 – 180 = 540 man-days
  • Now, total men working = 40 men
  • Time required to complete remaining work = 540 / 40 = 13.5 days
  • Total days taken = 6 (initial) + 13.5 = 19.5 ≈ 16 days

Sample Quantitative Aptitude Question

Welcome to your Time and Work (Quantitative Aptitude Question)

Year of passing
A can complete a task in 12 days, and B can do the same in 18 days. How many days will they take together?

A can finish a job in 10 days. B is 50% more efficient than A. In how many days can B finish the same job?

A pipe fills a tank in 5 hours, while another empties it in 8 hours. How long will it take to fill the tank if both are open?

A, B, and C can complete a work in 10, 15, and 20 days, respectively. How long will they take together?

A can do a job in 20 days. After working 4 days, A leaves, and B completes the remaining work in 12 days. How long would B alone take to complete the job?

Conclusion

Time and Work problems are essential in quantitative aptitude, testing a candidate’s ability to handle efficiency-based calculations. Understanding concepts like individual and group work efficiency, LCM method, and inverse proportionality can significantly improve problem-solving speed. Practicing a variety of questions helps in mastering different scenarios, such as pipes and cisterns or workforce changes.

Time and Work